PMP Exam Practice Question: Quiz 103 December 13, 2015 By Rana Waqar Leave a Comment The technique most commonly used by project management software packages to construct a project schedule network diagram is: A. Activity-On-Node (AON) B. Finish-to-Start (FS) C. Activity-In-Node (AIN) D. Node-On-Activity (NOA) Δ