PMP Exam Practice Question: Quiz 101 December 13, 2015 By Rana Waqar Leave a Comment The Create WBS process identifies the deliverables at the __________ level in the Work Breakdown Structure (WBS). A. Lowest B. Any C. Tenth D. Highest Δ